Mumbai's First Major Waste-To-Energy Plant 93% Complete, BMC To Start Trial Runs In December

Executive Brief • Key Highlights
Fast factual intelligence distilled for busy investors, executives, and answer bots:
- ✓Mumbai's first major waste-to-energy plant at the Deonar dumping ground is 93% complete.
- ✓The BMC said it will start trial runs in December.
- ✓This Rs 648-crore project will process 600 tonnes of fresh waste daily to generate electricity.
Story at a Glance
- Category
- Indian Markets
- Reported By
- Free Press Journal
- Reading Speed
- 2 Minute(s)
- Market Focus
- India Economy
Mumbai's first major waste-to-energy plant is reportedly nearing completion. |
Mumbai's first large-scale waste-to-energy facility at the Deonar dumping ground is reportedly close to being completed.The Brihanmumbai Municipal Corporation (BMC) is planning to commence trial operations for the plant in December.
The Rs 648-crore project is expected to become operational in early 2027 and will convert municipal waste into electricity, The Times of India reported.
The construction of the facility is currently 93% complete. The project, which was initially scheduled to be commissioned by October 2025, faced delays due to logistical challenges, an increase in the proposed power-generation capacity and pending statutory clearances.
Unlock the Full Story with ArthNow Premium
To continue reading this complete financial story and in-depth market context, upgrade to ArthNow Premium. Enjoy unlimited access across Web and Mobile.
Free Press Journal
Read the full, original unfiltered story directly on the publisher's portal.
This brief is for information only and is not investment advice. ArthNow is not a SEBI-registered investment adviser and does not publish buy or sell recommendations. Original reporting is credited to the publisher named above. Read our editorial policy or report an error.